Skip to main content
Course and syllabus guidance

Cambridge International AS & A Level · P5 · structured

Make a usable risk assessment

A2 practical 2: connect each precaution to an actual hazard · Original GioPhysics question with a detailed, mark-by-mark answer guide.

Demand
demanding
Marks
8
Topics
2
Answer
Complete
structured8 marks

For a vertical spring on a stand and clamp carrying a hanging mass and the proposed 6.0 V, 20 ohm, 0.25 W resistor circuit, write two hazard-exposure-control entries, one mechanical and one electrical. Calculate resistor power, reject or accept the operating point, and propose a quantified lower -power alternative. Give a stop condition.

  1. (a)

    Write mechanical and electrical risk entries.

    4 marks
  2. (b)

    Evaluate and revise resistor operating power.

    3 marks
  3. (c)

    Give a stop condition.

    1 mark
Ready to self-mark?Reveal the detailed answer guide
Answer overviewFalling mass controlled with secure stand/tray/clear path; resistor heating controlled by lower voltage/current limit. 1.8 W is unsuitable; 1.0 V gives 0.050 W. Stop for unstable clamp, permanent extension or unexpected heating.
01

(a)

4 marks

Write mechanical and electrical risk entries.

How to approach it

Identify what the question is testing, organise the response into distinct mark-earning points, and make every conclusion traceable to a physical principle or to the evidence supplied.

  1. 1

    Concrete exposure-control pair for falling mass and overheating/short circuit.

02

(b)

3 marks

Evaluate and revise resistor operating power.

How to approach it

Identify what the question is testing, organise the response into distinct mark-earning points, and make every conclusion traceable to a physical principle or to the evidence supplied.

  1. 1

    1.8 W exceeds 0.25 W; e.g. 1.0 V produces 0.050 W.

03

(c)

1 mark

Give a stop condition.

How to approach it

Identify what the question is testing, organise the response into distinct mark-earning points, and make every conclusion traceable to a physical principle or to the evidence supplied.

  1. 1

    Unexpected heating, unstable clamp or permanent extension triggers stopping and teacher review.

Complete marking guidance

Use these worked steps alongside the part-by-part answers. They explain the method and mark allocation; they do not add extra marks.

  1. Two complete hazard/exposure/control links: 4 marks.
  2. P=1.8 W and explicit rejection compared with 0.25 W rating: 2 marks.
  3. A quantified safe-power proposal such as 1.0 V giving 0.050 W, subject to school check: 1 mark.
  4. Relevant stop condition: 1 mark.

Private on this device

Your self-assessment

Compare your work with the guide. This is your own rating, not an awarded exam mark.